The Government is developing a new cruise terminal at the former Kai Tak Runway. It has two alongside berths, which can accommodate the biggest cruise vessel in the world. Here are some development parameters of the new cruise terminal -
No. of cruise vessels that can be berthed |
Two or more cruise vessels including mega vessels |
Length overall |
360 metres |
Length of apron area |
850 metres |
Gross tonnage |
220 000 tonnes |
Displacement tonnage |
110 000 tonnes |
Depth of water |
12 metres - 13 metres (for dredging) |
Air draft restriction |
No |
Customs, immigration and health quarantine operation |
Clearing up to 3 000 passengers per hour |
The cruise terminal will be developed under two contracts. The first is the site formation works contract, involving the construction of berthing facilities of the cruise terminal. The second is the cruise terminal building works contract, including the customs, immigration and health quarantine facilities and other supporting facilities.
Site formation
The site formation works have commenced. A Ground Breaking Ceremony of the Site Formation for the Kai Tak Cruise Terminal was held on 23 December 2009, signifying the commencement of work of the new cruise terminal and a milestone in the development of cruise tourism in Hong Kong.
We plan to provide service to the cruise operators as soon as the first berth is completed around mid-2013. The second berth will be ready for berthing medium-sized cruise vessels in 2014. After relocation of submarine gas mains by the Hong Kong and China Gas Company Limited, the second berth will be able to accommodate mega cruise vessels in 2015.
Cruise terminal building
Assessment of the tender submissions of the design-and-build contract for the cruise terminal building has been completed, and the funding application for cruise terminal building and ancillary facilities was also approved by the LegCo Finance Committee on 30 April 2010. Construction works is scheduled to commence in May 2010. The completion time of the terminal building will be advanced from the originally planned 2014/15 to within 2013, with the target to synchronise with the opening of the first berth around mid-2013. |